LAB 002 · Case Study

Scenario-Based Planning: Simulate Before You Commit

Four sequencing scenarios compared: baseline, acceleration, fewer interfaces, resource constraints. An independent study inspired by construction simulation tools such as ALICE.

For: Planning Managers, EPCM · Synthetic data · Scenarios

Executive summary

Before committing resources, comparing several construction sequences lets you decide on explicit criteria: finish date, peak workforce, number of interfaces, risk exposure.

Generative scheduling tools such as ALICE automate this exploration. This independent demonstrator applies the same logic by hand, on synthetic data.

The problem

A fictional four-zone industrial building must be delivered in 52 weeks. The reference schedule meets the date, but it concentrates the interfaces between civil works, utilities and equipment in Zones 2 and 3, and assumes a crane available at all times.

Method

  • Set the objective and comparison criteria before building the scenarios.
  • Start from a validated reference schedule, with its resource constraints and interfaces.
  • Change one assumption at a time: sequencing, resources, zoning.
  • Recalculate each scenario and record the same indicators.
  • Present the trade-offs without naming a "best" scenario in the abstract.

Four scenarios compared

ScenarioAssumptionFinish (wk)Peak workforceActive interfacesIndicative cost
A · BaselineReference sequence5212034Reference
B · AccelerationDouble shift on structural works4716538+6%
C · Fewer interfacesZone-by-zone handover5011021+1%
D · Resource constraintsSingle crane, workforce capped at 90579029−2%
Synthetic data. Costs are relative assumptions, not estimates.

B saves 5 weeks but raises the peak workforce by 38% and adds interfaces: congestion risk goes up. C saves 2 weeks while sharply cutting interfaces, at a small extra cost. D shows what an unresolved crane constraint costs in time.

Reading it for a decision

C is the most robust scenario if congestion is the main risk. B is justified if the finish date has high commercial value. The decision depends on what a week saved is worth to the owner, and the analysis should make that value explicit.

Limitations

  • Synthetic data: the differences illustrate the method, not a transferable result.
  • Productivity is assumed constant across scenarios.
  • Costs are relative orders of magnitude.
  • A generative scheduling tool explores far more combinations than four hand-built scenarios.
  • Independent study: no integration or partnership with ALICE Technologies.