Executive summary
An extension of time request blends three questions that are often confused. Did the event delay the contractual milestones (impact)? Does the contract give a right to an extension for this kind of event (entitlement)? Does the owner grant the extension (decision)?
This note addresses the first question with a Time Impact Analysis on a fictional project, and shows where technical analysis stops.
The problem
On a fictional industrial construction project, access to Zone B, fixed in the contract, is given 30 working days late. The contractor requests a 30-day extension. The owner must decide on an objective basis.
Method
- Validate the reference schedule: accepted baseline, last update before the event, logic and float checked.
- Model the event as a fragnet: a "Zone B access" activity at the actual access date, linked to the activities it drives.
- Insert the fragnet into the update preceding the event, then recalculate.
- Compare milestone dates before and after insertion: the difference is the modelled impact.
- Examine contractor-caused delays over the same period and their effect on the same milestones.
- Document assumptions, sources and limitations in a traceable report.
This follows Time Impact Analysis, an established method for contemporaneous delay analysis. For retrospective analysis, methods are classified as observational or modelled, static or dynamic, additive or subtractive: the choice depends on the available data and the contract.
Worked example
| Item | Value | Comment |
|---|---|---|
| Late access to Zone B | 30 working days | Contract date versus actual access date |
| Total float on the Zone B path | 8 working days | Validated update preceding the event |
| Modelled impact on milestone M3 | 22 working days | 30 − 8: float absorbs part of the delay |
| Contractor delay, Zone A | 6 working days | Path with 15 days of float: no effect on M3 |
| Extension requested | 30 working days | Ignores the available float |
The analysis shows a 22-working-day impact on milestone M3, not 30. The contractor's Zone A delay does not reach that milestone, so there is no concurrent delay in the sense of two causes affecting the same milestone.
Impact, entitlement, decision
The 22 days are a technical result. Entitlement depends on the contract: allocation of site access risk, notice procedure and time bars, float ownership and concurrent delay rules.
The decision to grant all or part of the extension belongs to the owner or its representative. The planner informs that decision; the planner does not make it.
Limitations
- The result is only as reliable as the reference schedule (see LAB 003).
- Float ownership is a contractual matter: it is assumed shared here.
- A prospective analysis models an expected impact; the actual impact is measured later on the as-built.
- A pure CPM analysis does not capture disruption effects on productivity.
- With several events, the order in which fragnets are inserted affects the result.