Executive summary
A critical path is only as reliable as the schedule behind it. A widely used grid of 14 checks provides a simple way to test logic, float, constraints and schedule performance.
They flag weaknesses; they do not prove a schedule is realistic.
The problem
A schedule can show a comfortable finish date while relying on imposed constraints, missing links or overly long durations. The calculated critical path then becomes an artefact of the model rather than a picture of the project.
The 14 checks
| # | Check | Usual threshold | What it reveals |
|---|---|---|---|
| 1 | Logic | ≤ 5% of activities missing a predecessor or successor | Dangling activities, incomplete critical path |
| 2 | Leads (negative lags) | 0 | Artificial overlaps, logic hard to follow |
| 3 | Lags | ≤ 5% of relationships | Durations hidden in links |
| 4 | Relationship types | ≥ 90% Finish-to-Start | Logic that is hard to read |
| 5 | Hard constraints | ≤ 5% of activities | Imposed dates that distort float |
| 6 | High float | ≤ 5% above 44 working days | Missing logic |
| 7 | Negative float | 0 | Milestones that no longer hold |
| 8 | High duration | ≤ 5% above 44 working days | Activities too coarse to manage |
| 9 | Invalid dates | 0 | Forecasts in the past, actuals in the future |
| 10 | Resources | Indicator, no threshold | Schedule not tied to resources |
| 11 | Missed tasks | ≤ 5% | Activities finished after their baseline finish |
| 12 | Critical path test | Pass | An injected delay must move the finish by the same amount |
| 13 | CPLI | ≥ 0.95 | Ability to hold the finish date |
| 14 | BEI | ≥ 0.95 | Execution pace against the baseline |
CPLI and BEI in practice
CPLI = (remaining critical path length + critical path total float) / remaining critical path length. With 200 days remaining and −10 days of float: CPLI = 190 / 200 = 0.95, right at the threshold.
BEI = activities completed / activities whose baseline finish has passed. With 180 completed out of 200 due: BEI = 0.90. The project is delivering 90% of what was planned to date.
Limitations
- The thresholds come from US defence contracting: an industrial project may justify other values.
- Long durations are normal for fabrication or procurement if they are documented.
- A schedule can pass all 14 checks and still be unrealistic: durations and logic also need review by the disciplines.
- These checks complement, rather than replace, a detailed review of the critical path.