Why Your Critical Path Cannot Be Trusted

Fourteen quality checks applied to a sample schedule: what each metric reveals, its thresholds, and what it does not tell you.

For: Head of Project Controls · Sample schedule · Schedule quality

Executive summary

A critical path is only as reliable as the schedule behind it. A widely used grid of 14 checks provides a simple way to test logic, float, constraints and schedule performance.

They flag weaknesses; they do not prove a schedule is realistic.

The problem

A schedule can show a comfortable finish date while relying on imposed constraints, missing links or overly long durations. The calculated critical path then becomes an artefact of the model rather than a picture of the project.

The 14 checks

#CheckUsual thresholdWhat it reveals
1Logic≤ 5% of activities missing a predecessor or successorDangling activities, incomplete critical path
2Leads (negative lags)0Artificial overlaps, logic hard to follow
3Lags≤ 5% of relationshipsDurations hidden in links
4Relationship types≥ 90% Finish-to-StartLogic that is hard to read
5Hard constraints≤ 5% of activitiesImposed dates that distort float
6High float≤ 5% above 44 working daysMissing logic
7Negative float0Milestones that no longer hold
8High duration≤ 5% above 44 working daysActivities too coarse to manage
9Invalid dates0Forecasts in the past, actuals in the future
10ResourcesIndicator, no thresholdSchedule not tied to resources
11Missed tasks≤ 5%Activities finished after their baseline finish
12Critical path testPassAn injected delay must move the finish by the same amount
13CPLI≥ 0.95Ability to hold the finish date
14BEI≥ 0.95Execution pace against the baseline
44 working days is roughly two months.

CPLI and BEI in practice

CPLI = (remaining critical path length + critical path total float) / remaining critical path length. With 200 days remaining and −10 days of float: CPLI = 190 / 200 = 0.95, right at the threshold.

BEI = activities completed / activities whose baseline finish has passed. With 180 completed out of 200 due: BEI = 0.90. The project is delivering 90% of what was planned to date.

Limitations

  • The thresholds come from US defence contracting: an industrial project may justify other values.
  • Long durations are normal for fabrication or procurement if they are documented.
  • A schedule can pass all 14 checks and still be unrealistic: durations and logic also need review by the disciplines.
  • These checks complement, rather than replace, a detailed review of the critical path.