Executive summary
When a project slips, a credible recovery plan starts from a schedule diagnosis, identifies what actually drives the delay, then compares options valued in time, cost and risk. It is then managed with a few indicators, week by week.
The problem
On a fictional industrial project, the forecast finish slips by 9 weeks over four updates. Each monthly review records the delay without recovering it.
Diagnosis
- Check schedule quality (LAB 003) before drawing conclusions.
- Track the milestone trend from one update to the next.
- Identify the critical path and the paths with less than 10 days of float.
- Separate issues of logic, resources, procurement and pending decisions.
Mitigation options
| Option | Lever | Estimated gain | Cost | Risk |
|---|---|---|---|---|
| A · Commissioning preparation during works completion | Fast-tracking | 3 wks | Low | Medium |
| B · Second shift on HVAC and electrical packages | Crashing | 4 wks | High | Medium |
| C · Expedited shipping of critical equipment | Procurement | 2 wks | Medium | Low |
| D · Zone-by-zone handover | Phasing | 3 wks on the 1st milestone | Low | Low, change order needed |
The gains do not add up: each option changes the critical path. Modelled in the schedule, the A + C + D combination recovers 7 of the 9 weeks. The remaining 2 weeks are either accepted or covered by option B if their value justifies it.
Managing the recovery
- Approve the recovery plan as a working schedule, without overwriting the contractual baseline.
- Track critical activity completion, float erosion and milestone forecasts every week.
- Revisit the options if two consecutive updates show further slippage.
- Re-baseline only after formal agreement on a new reference.
Limitations
- Estimated gains depend on productivity and actual resource availability.
- Fast-tracking increases rework risk if interfaces are not under control.
- Some options, such as zone-by-zone handover, require contractual agreement.