LAB 004 · Project Controls Guide

From Baseline to Recovery Plan

Diagnosing a slipping project, mitigation scenarios, time, cost and risk trade-offs, then tracking whether the actions work.

For: Owners, Project Directors · Fictional project · Recovery

Executive summary

When a project slips, a credible recovery plan starts from a schedule diagnosis, identifies what actually drives the delay, then compares options valued in time, cost and risk. It is then managed with a few indicators, week by week.

The problem

On a fictional industrial project, the forecast finish slips by 9 weeks over four updates. Each monthly review records the delay without recovering it.

Diagnosis

  • Check schedule quality (LAB 003) before drawing conclusions.
  • Track the milestone trend from one update to the next.
  • Identify the critical path and the paths with less than 10 days of float.
  • Separate issues of logic, resources, procurement and pending decisions.

Mitigation options

OptionLeverEstimated gainCostRisk
A · Commissioning preparation during works completionFast-tracking3 wksLowMedium
B · Second shift on HVAC and electrical packagesCrashing4 wksHighMedium
C · Expedited shipping of critical equipmentProcurement2 wksMediumLow
D · Zone-by-zone handoverPhasing3 wks on the 1st milestoneLowLow, change order needed
Fictional project. Gains estimated option by option, before combining.

The gains do not add up: each option changes the critical path. Modelled in the schedule, the A + C + D combination recovers 7 of the 9 weeks. The remaining 2 weeks are either accepted or covered by option B if their value justifies it.

Managing the recovery

  • Approve the recovery plan as a working schedule, without overwriting the contractual baseline.
  • Track critical activity completion, float erosion and milestone forecasts every week.
  • Revisit the options if two consecutive updates show further slippage.
  • Re-baseline only after formal agreement on a new reference.

Limitations

  • Estimated gains depend on productivity and actual resource availability.
  • Fast-tracking increases rework risk if interfaces are not under control.
  • Some options, such as zone-by-zone handover, require contractual agreement.